The company adding 12 flats on top of Helena House, Sutton High Street, wants three years from a new decision to finish them. A decision is due by 13 January.

The company adding two floors and 12 flats on top of Helena House, at the northern end of Sutton High Street, has asked for three years from a new decision to finish the work. Its planning agent says telecoms equipment on the roof and a building safety approval are holding up the build. The council aims to decide by Wednesday 13 January.

Sutton Council validated the application on Wednesday 18 November, in the week starting 16 November. It is on the council’s weekly list of new applications.

More time to finish 12 flats on Helena House

The application, DM2026/01326, is from Helena House Developments Limited, at 348 to 352 High Street.

The 12 flats were allowed on appeal on 7 February 2025, under national permitted development rules for adding homes on top of existing buildings. The approval, reference DM2024/00476, covers two new floors with 12 self-contained flats and parking. In September 2026 the council allowed changes to the roof stairwell and to the front and rear windows, under reference DM2025/01390.

Under those national rules, the extra floors have to be finished within three years of the original approval. The cover letter from the agent, Allsop, says that leaves until February 2028, which it calls too little time. It asks the council for a new condition: the work must be finished within three years of the date of this decision.

The letter gives these reasons:

  • two telecoms operators still have equipment on the roof, under leases that ran out in 2013 and 2015, and it sits where the new floors would go;
  • the company has been talking to the operators and their site provider since January 2026; plans are being drawn up to move the equipment above the new floors, and separately to move it to a building the council owns;
  • once extended, Helena House will be taller than 18 metres, which makes it a higher-risk building under the Building Safety Act 2022;
  • the Building Safety Regulator must approve the building control application, known as Gateway 2, before the two new floors can start, and the letter says that is delayed.

The letter says work to convert the existing building is going ahead, and that the design and the number of flats would not change. It is in the application’s documents, with the 2025 appeal decision attached.

The council has not published a consultation date for this application.

Also applied for this week

  • The Grange, Beddington Park, London Road, Wallington: low-level lighting bollards along the entrance roads to The Grange. The heritage statement in the application’s documents says they are to make the entrances safer and easier to use after dark, with no changes to any historic building, wall or landscape feature, DM2026/01298. The council aims to decide by 12 January.
  • 292 High Street, Sutton: one lit fascia sign and one lit projecting sign, DM2026/00977.

How to comment

Comments go through Sutton Council’s planning register, on each application’s own page, before any consultation date shown there.